Roadway Repairs
Johnson Industrial Boulevard Roadway Repairs Tentative Schedule:
- Water service removal (NCGUD request) – COMPLETED
- Roadway milling – COMPLETED
- Binder mix placement – Thursday, 11/11/21 and Friday, 11/12/21
- Stonebrook undercut – COMPLETED
- Extruded curb installed – between Monday, 11/15/21 and Wednesday, 11/17/21
- Castings adjusted – between Monday,11/15/21 and Wednesday, 11/17/21
- Topsoil placement with seed and straw – Wednesday, 11/17/2021
- Sidewalk along Stonebrook installed – by Wednesday, 11/17/21
- Trail paving with surface – no later than Friday, 11/19/21
- Roadway surface – no later than Friday, 11/19/21
- Final striping – week of 11/22/21
- Erosion control removal – to be completed once grass is growing on disturbed area
*Due to weather conditions and shipping delays on materials, task end dates may vary.