Johnson Industrial Boulevard Roadway Repairs Tentative Schedule: 

  • Water service removal (NCGUD request) – COMPLETED
  • Roadway milling – COMPLETED
  • Binder mix placement – Thursday, 11/11/21 and Friday, 11/12/21
  • Stonebrook undercut – COMPLETED
  • Extruded curb installed – between Monday, 11/15/21 and Wednesday, 11/17/21
  • Castings adjusted – between Monday,11/15/21 and Wednesday, 11/17/21
  • Topsoil placement with seed and straw – Wednesday, 11/17/2021
  • Sidewalk along Stonebrook installed – by Wednesday, 11/17/21
  • Trail paving with surface – no later than Friday, 11/19/21
  • Roadway surface – no later than Friday, 11/19/21
  • Final striping – week of 11/22/21
  • Erosion control removal – to be completed once grass is growing on disturbed area

*Due to weather conditions and shipping delays on materials, task end dates may vary.